A brief inspection of the Building was made by the Building Board on 18th April 2012 to witness for themselves the progress of the construction works.
By the end of April, the roof of the building and the lift installation would be completed. Currently the contractor is doing three mock-up guest rooms for the Architect to finalise the colour scheme, etc. Laying of floor tiles, painting of walls and fixing of door & window frames are being done. The contractor might not be able to finish all works by mid-May as envisaged and might need a few more weeks to do so. Meanwhile we have told the contractor not to sacrifice quality of work for speed.
There will be a soft launch into the new building on 16th October 2012 during the Board of Management Meeting.
Dedication service will be held next year on 23rd April 2013.
We have yet to raise RM 4 million.